Funding limit reconciliation is a tool and technique used in which process?
A.
Control Costs
B.
Determine Budget
C.
Estimate Costs
D.
Control Budget
The Answer Is:
B
This question includes an explanation.
Explanation:
According to the PMBOKĀ® Guide, Funding Limit Reconciliation is a specific tool and technique of the Determine Budget process.
Definition: It is the process of comparing the planned expenditure of project funds against any limits on the commitment of funds for the project.
The Mechanism: Organizations often have constraints regarding the timing of fund disbursements (e.g., quarterly or annual budget caps). If the project ' s planned spending (the Cost Baseline) shows a spike that exceeds these limits, the project manager must reconcile the two.
Outcome of Reconciliation: To stay within the funding limits, the project manager may need to reschedule work. This often involves moving activities from a period of high spending to a period with more available funding by using scheduling constraints (such as " Must Start On " dates) within the project schedule.
Key Result: This process helps finalize the Cost Baseline, ensuring that the project ' s time-phased budget is not only realistic in terms of work but also financially viable based on the organization ' s cash flow.
Analysis of Other Options:
A. Control Costs: While this process involves monitoring the status of the project to update costs and managing changes to the cost baseline, the reconciliation of the total budget against funding limits is a planning activity performed during Determine Budget.
C. Estimate Costs: This process involves developing an approximation of the monetary resources needed to complete project activities. It provides the " raw data " (activity cost estimates) that are later aggregated in the Determine Budget process.
D. Control Budget: This is not a formal process name in the PMBOKĀ® Guide. The monitoring and controlling process for finances is officially called Control Costs.
CAPM PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"