According to the PMBOKĀ® Guide and the Standard for Project Management, effective communication is not just about the distribution of information, but the confirmation of understanding. In the Monitor Communications process, the project manager must ensure that the communication artifacts (like meeting outcomes) have achieved their intended purpose.
Why Choice C is correct:
Closing the Feedback Loop: The true measure of a meeting ' s effectiveness is whether the participants can act on the decisions made. By reviewing the actions with team members, the PM identifies gaps in understanding or misinterpretations that occurred during the meeting.
Interpersonal and Team Skills: This approach utilizes active listening and feedback, which are core power skills. It allows the PM to verify that " noise " did not interfere with the message and that the team is aligned on the path forward.
Immediate Correction: Unlike waiting for a retrospective, this provides immediate insight into whether the planning session was successful or if the team is still confused about their responsibilities.
Analysis of other options:
A (Send the meeting minutes): Sending minutes is a standard administrative task (distribution), but it is passive. Simply having information " readily available " does not mean it was understood or that the meeting was effective in influencing behavior.
B (Wait for the phase retrospective): While retrospectives are excellent for process improvement, waiting until the end of a phase is too late to assess a specific planning meeting ' s effectiveness. The project may have already suffered from misalignment by then.
D (Consult the communications management plan): The plan defines how meetings should be conducted and what the criteria are, but it is a static document. Consulting it doesn ' t tell you how well a specific meeting actually went in practice.
Key Concept: The Project Management Institute (PMI) emphasizes that " Communication = Understanding. " Choice C is the most proactive and direct way to assess if the meeting ' s objectives were met by checking the " output " (team understanding) against the " input " (the meeting content).