Pre-Summer Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: ac4s65

During the execution of a project, a stakeholder asks a project manager whether the project...

During the execution of a project, a stakeholder asks a project manager whether the project is falling behind or ahead of its baseline schedule. The project manager calculates the earned value analysis (EVA) schedule variance and it comes out to be zero. Which of the following is correct about the EVA schedule variance?

A.

It is calculated incorrectly, as it cannot be zero for an in-flight project; otherwise the project is completed.

B.

Change it to a negative value to show that the project is falling behind.

C.

Zero is a perfectly valid value for an in-flight project; hence share the zero value with the stakeholder.

D.

Change it to a positive value to show that the project is ahead of its baseline schedule.

CAPM PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now CAPM pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"