What does an S-curve from a Monte Carlo analysis show?
Cumulative probability distribution representing probability of achieving a particular outcome
Individual project risks or uncertainties that have the most potential impact on outcome
Best alternative out of the possible solutions, incorporating associated risks and opportunities
Diagram for all project uncertainties and their influence over a period of time