Which of the following can be used as an input for Define Scope?
A.
Product analysis
B.
Project charter
C.
Scope baseline
D.
Project scope statement
The Answer Is:
B
This question includes an explanation.
Explanation:
According to the PMBOKĀ® Guide, the Define Scope process is the process of developing a detailed description of the project and product. Since this process occurs early in the Planning Process Group, it relies on high-level guidance to establish boundaries.
The Project Charter as an Input: The Project Charter is a key input because it provides the high-level project description, product characteristics, and approval requirements. It contains the " boundaries " set during the initiation phase that the project manager must now elaborate into a detailed scope.
Other Key Inputs:
Project Management Plan (specifically the Scope Management Plan).
Project Documents (such as the Requirements Documentation and Risk Register).
Enterprise Environmental Factors (EEF).
Organizational Process Assets (OPA).
The Goal: The goal of using these inputs in " Define Scope " is to transition from a high-level vision (the Charter) to a specific, detailed set of deliverables and work.
Analysis of Other Options:
A. Product analysis: This is a Tool and Technique used during the Define Scope process (used to translate high-level product descriptions into tangible deliverables), not an input.
C. Scope baseline: This is an Output of the Create WBS process. It consists of the approved scope statement, WBS, and WBS dictionary. It cannot be an input to Define Scope because Define Scope must happen first to create the scope statement.
D. Project scope statement: This is the primary Output of the Define Scope process. It documents the entire scope, including project and product scope, deliverables, and exclusions.
CAPM PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"