Based on the following metrics: EV= $20,000, AC= $22,000, and PV= $28,000, what is the project CV?
A.
-8000
B.
-2000
C.
2000
D.
8000
The Answer Is:
B
This question includes an explanation.
Explanation:
Based on the principles of Earned Value Management (EVM) found in the PMBOKĀ® Guide, the Cost Variance (CV) is a measure of cost performance on a project.
Formula: $CV = EV - AC$
Calculation: Given the metrics:
Earned Value ($EV$) = $\$20,000$
Actual Cost ($AC$) = $\$22,000$
$CV = 20,000 - 22,000 = -2,000$
Interpretation:
A negative CV ($-2,000$ in this case) indicates that the project is over budget. It means the actual cost spent to date is higher than the value of the work performed.
A positive CV would indicate that the project is under budget.
A CV of zero would indicate that the project is exactly on budget.
Note: The Planned Value ($PV$) of $\$28,000$ is used for calculating Schedule Variance ($SV = EV - PV$), but it is not used in the calculation for Cost Variance.
CAPM PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"