Which of the following are three inputs to the risk register?
A.
Risk register updates, stakeholder register, and quality management plan
B.
Communication management plan, enterprise environmental factors, and activity duration estimates
C.
Risk management plan, activity cost estimates, and project documents
D.
Project scope statement, organizational process assets, and scope baseline
The Answer Is:
C
This question includes an explanation.
Explanation:
According to the PMBOKĀ® Guide, the Identify Risks process is where the Risk Register is initially created. To identify risks effectively, the project manager must look at various components of the project management plan and other project artifacts.
Risk Management Plan: This is a vital input because it provides the " how-to " for risk activities. It defines the roles and responsibilities, the budget for risk activities, and the categories of risk (often found in the Risk Breakdown Structure or RBS).
Activity Cost Estimates: These are reviewed to identify risks associated with the financial aspects of the project. If an estimate is particularly aggressive or based on volatile market prices, it represents a potential risk that needs to be captured in the register.
Project Documents: This is a broad category that includes the requirements documentation, schedule, and other logs. These documents provide the specific details of what the project is trying to achieve, which allows the team to identify specific threats or opportunities related to those goals.
Other Key Inputs:
Scope Baseline: Used to identify potential risks to the project ' s boundaries.
Schedule Management Plan: Used to identify risks related to timelines and milestones.
Analysis of Other Options:
A. Risk register updates: This is an output of many risk-related processes (like Perform Qualitative Risk Analysis or Plan Risk Responses), not an input to the creation of the initial register.
B. Communication management plan: While communication is important, it is not listed as a primary input specifically used to identify technical or project risks for the register.
D. Project scope statement / Scope baseline: While these are valid inputs, Organizational Process Assets (OPAs) are general environmental factors or historical templates, and this grouping is less comprehensive than option C in terms of the specific project data needed for risk identification.
CAPM PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"