Which of the following are processes associated with Project Cost Management?

Which of the following are processes associated with Project Cost Management?

A.

Develop Costs. Estimate Costs, Determine Budget. Control Costs

B.

Develop Budget, Determine Budget, Determine Risks, Control Costs

C.

Plan Cost Management, Estimate Costs. Determine Budget. Control Costs

D.

Plan Budget Management. Determine Budget, Create Cost Accounts. Control Costs