Which of the following is an output of the Monitor and Control Project Work process?
A.
Change requests
B.
Performance reports
C.
Organizational process assets
D.
Project management plan
The Answer Is:
A
This question includes an explanation.
Explanation:
According to the PMBOKĀ® Guide, the Monitor and Control Project Work process is the process of tracking, reviewing, and reporting the overall progress to meet the performance objectives defined in the project management plan.
Change Requests: As a result of comparing actual performance against the project management plan, variances may be identified. If these variances are significant or if the project manager identifies opportunities for improvement, Change Requests are issued as a primary output.
These requests may include corrective action (to realign performance with the plan), preventive action (to reduce the probability of negative impacts), or defect repair.
All change requests generated here are processed through the Perform Integrated Change Control process for approval or rejection.
Other Key Outputs:
Work Performance Reports: These are the physical or electronic representation of work performance information compiled into project documents, intended to generate decisions, actions, or awareness.
Project Management Plan Updates: Changes to any component of the plan.
Project Documents Updates: Such as the cost and schedule forecasts, issue logs, and the risk register.
Comparison with other options:
B. Performance reports: In older versions of the PMBOKĀ® Guide, " Performance Reports " was a specific output. However, in current standards, the output is specifically termed Work Performance Reports. While similar, Change Requests remains the most definitive and functional output when performance deviates from the baseline.
C. Organizational process assets: These are typically inputs to this process (providing the reporting templates or monitoring policies). While the process might lead to " Updates " to OPAs (like lessons learned), the assets themselves are not an output created by the process.
D. Project management plan: This is the primary input that provides the baselines against which the project is monitored. While the plan may be updated as a result of this process, the plan itself is not a new output generated by monitoring.
CAPM PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"