According to the PMBOK® Guide, specifically the Develop Team process (formerly Develop Project Team), this process focuses on improving competencies, team member interaction, and the overall team environment to enhance project performance.
Team Performance Assessments: This is a primary output of the process. As the project manager implements various development strategies (such as training, team-building activities, and ground rules), they must evaluate the effectiveness of these efforts.
Evaluation Criteria: The success of the team development is measured against formal or informal assessments of the team’s effectiveness. Criteria include:
Improvements in individual skills (technical or soft skills).
Improvements in team competencies (working better as a collective).
Reduced staff turnover rate.
Increased team cohesiveness and improved communication.
Impact on the Project: By assessing performance, the project manager can identify the specific training or coaching required to close gaps and ensure the project objectives are met.
Comparison with other options:
A. Change requests: While change requests can occur in many processes, they are typically a " by-product " rather than the defining primary output of the Develop Team process.
C. Project staff assignments: This is an output of the Acquire Resources (Acquire Project Team) process. It identifies who is on the team before the development process begins.
D. Project documents updates: While project documents (like the resource calendar) may be updated, Team Performance Assessments is the unique, core functional output specifically associated with the " Develop " phase of human resource management.
CAPM PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"