Which of the following is an output of Direct and Manage Project Execution?
A.
Project management plan
B.
Change request status updates
C.
Organizational process assets updates
D.
Work performance information
The Answer Is:
D
This question includes an explanation.
Explanation:
According to the PMBOKĀ® Guide, the Direct and Manage Project Execution (now commonly referred to as Direct and Manage Project Work) process is the stage where the project team performs the work defined in the project management plan to achieve the project ' s objectives.
Work Performance Information: This is a primary output of this process. It includes data on the status of project activities being performed to accomplish the project work. This information covers deliverables status, schedule progress, and costs incurred.
Other Key Outputs: Other critical outputs of this process include Deliverables (the actual products or results), Change Requests, and updates to the Project Management Plan and Project Documents.
Analysis of Other Options:
A. Project management plan: This is the primary input to this process. While updates to the plan can be an output, the plan itself is created during the planning phase.
B. Change request status updates: This is typically an output of the Perform Integrated Change Control process, where change requests are approved, deferred, or rejected.
C. Organizational process assets updates: While these can occur in many processes, they are more common as outputs in the Closing phase or specific Monitoring and Controlling processes rather than the core " Execution " output highlighted in this context.
CAPM PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"