An organization is faced with increasing demand from the board of directors.

An organization is faced with increasing demand from the board of directors. They say budgets are flexible as long as the work gets completed.

What project management approach should the organization use?

A.

Predictive

B.

Hybrid

C.

Iterative

D.

Adaptive