Which of the following is an input to the Perform Qualitative Risk Analysis process?
A.
Risk register
B.
Risk data quality assessment
C.
Risk categorization
D.
Risk urgency
The Answer Is:
A
This question includes an explanation.
Explanation:
According to the PMBOKĀ® Guide, the Perform Qualitative Risk Analysis process is the process of prioritizing risks for further analysis or action by assessing and combining their probability of occurrence and impact.
To conduct this analysis, the project team requires specific inputs to provide the necessary data and framework:
Risk Register: This is the primary input. The risk register is created during the Identify Risks process and contains the list of identified risks that now need to be qualified (scored) based on their probability and impact.
Risk Management Plan: Provides the roles, responsibilities, budgets, and schedule activities for risk management, as well as the definitions of probability and impact levels.
Scope Baseline: Used to evaluate the potential impact of risks on the project ' s scope and deliverables.
Organizational Process Assets: Includes data from previous, similar projects and the organization ' s risk categories.
Analysis of Other Options:
B. Risk data quality assessment: This is a tool and technique used during the process to evaluate the degree to which the data about risks is useful for risk management.
C. Risk categorization: This is a tool and technique used to group risks by their sources (e.g., using a Risk Breakdown Structure) to identify the areas of the project most exposed to uncertainty.
D. Risk urgency: This is an assessment/output criteria used during the process to identify risks that require near-term responses.
CAPM PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"