According to the PMBOKĀ® Guide (Project Integration Management), the Close Project or Phase process is the process of finalizing all activities for the project, phase, or contract. To formally close a project or phase, the project manager must have confirmation that the work was completed according to the requirements.
Accepted Deliverables as an Input: Deliverables that have been signed off through the Validate Scope process are considered " Accepted Deliverables. " These are a primary input to closing because you cannot formally close a project or phase until the customer or sponsor has officially accepted the results of the work.
Transition of Ownership: Once these accepted deliverables enter the closing process, they are transitioned to the next phase or to production/operations.
Other Key Inputs: Other inputs include the Project Charter, the Project Management Plan, and Project Documents (such as the lesson learned register and milestone list).
Analysis of Distractors:
B. Final products or services: This is an output of the Close Project or Phase process. It represents the actual transition of the accepted product to the customer.
C. Document updates: While project documents are updated during this process (e.g., the Lessons Learned Register), " Project Document Updates " is categorized as an output, not a primary input required to start the closing activities.
D. Work performance information: This is an output of various Monitoring and Controlling processes (like Control Schedule or Control Costs). While it is used to manage the project, it is not the specific administrative trigger or requirement for the formal closing process.
CAPM PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"