An adaptive project team is grooming the backlog for the next iteration.

An adaptive project team is grooming the backlog for the next iteration. What does the team need to document in the user stories to determine the work needed to complete each story?

A.

Team velocity in past iterations

B.

Related epics of each story

C.

Product owner's priorities

D.

Detailed acceptance criteria