A project veers off track due to scope creep.

A project veers off track due to scope creep. The project management team requests an immediate response from the major stakeholders.

What should the project manager do next to avoid project failure?

A.

Adopt a change management approach and delay the project to decide on the direction.

B.

Develop a focus group to face the issue and decide on the appropriate direction.

C.

Request a meeting with top management to state concerns about their ability to handle the situation.

D.

Delay the project by adopting a fast-fail approach, mitigating the risk of having a bigger impact on the company.