A project reports an earned value (EV) of USS45 for work completed with an actual...

A project reports an earned value (EV) of USS45 for work completed with an actual cost (AC) of US$40. What is the cost performance index (CPI)?

A.

0.88

B.

1.12

C.

0.58

D.

1.58