A project manager is working on project cost management.

A project manager is working on project cost management. The following information is current.

* Planned value = 30

* Actual cost = 35

* Earned value = 28

Considering this data, which project indicator is correct?

A.

Schedule Variance (SV) = 2

B.

Cost Performance Index (CPI) = 0.80

C.

Schedule Performance Index (SPI) = 1.93

D.

Cost Variance (CV) = 7