A project manager is preparing a monthly status report for the project, which includes project performance compared to the baseline schedule. How can the project manager calculate the schedule variance (SV) for tasks on the critical path?

A.

Earned Schedule + Actual Time

B.

Actual Time - Earned Schedule

C.

Planned Value - Earned Value

D.

Earned Value - Planned Value