A project manager is appointed full-time to a project and is given full-time administrative staff...

A project manager is appointed full-time to a project and is given full-time administrative staff and full-time project team members. This situation describes which type of organizational structure?

A.

Projectized

B.

Weak matrix

C.

Functional

D.

Balanced matrix