A project is delivering an integrated solution to an external client on a fixed-price contract. The project has a significant technical component and has a dedicated technical project manager working with a business program manager and the client ' s project manager. The technical lead is requesting two new developers.
Which plan should the project manager use to identify who is responsible for finding the budget for additional developers?