You are managing a project that will implement a new MARKETING software package.

You are managing a project that will implement a new MARKETING software package. You have assigned the resources and want to keep the IT manager in the loop by informing him or her of your decisions. Which type of organizational structure are you working in?

A.

Pi'ojectized

B.

Strong Matrix

C.

Weak Matrix

D.

Functional