New Year Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: ac4s65

What is the status of a project if the Cost Performance Index is 1.

What is the status of a project if the Cost Performance Index is 1.25 and the Schedule Performance Index is 0.75?

A.

Under budget and behind schedule

B.

Over budget and ahead of schedule

C.

Under budget and ahead of schedule

D.

Over budget and behind schedule

CA0-001 PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now CA0-001 pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"