What is the status of a project if the Cost Performance Index is 1.

What is the status of a project if the Cost Performance Index is 1.25 and the Schedule Performance Index is 0.75?

A.

Under budget and behind schedule

B.

Over budget and ahead of schedule

C.

Under budget and ahead of schedule

D.

Over budget and behind schedule