Which process must occur after a project manager has been assigned to the project?
A.
Collect Requirements
B.
Develop the project charter
C.
Develop the project statement of work
D.
Develop project closing document
The Answer Is:
A
This question includes an explanation.
Explanation:
The Collect Requirements process occurs during project planning. Other options occur during project initiation. Option D is associated with project closing. Collect Requirements is the best option.