The project is consuming fewer resources than anticipated
B.
The project is using fewer resources than anticipated.
C.
The project is falling behind.
D.
The project is running ahead of schedule.
The Answer Is:
A
This question includes an explanation.
Explanation:
If your cost performance index is above 1.0, it indicates that you have costs that are less then estimated; so doing good. Option A is BEST fit for this CPI = EV/AC (Earned value/ Actual cost