The project is consuming fewer resources than anticipated
B.
The project is using fewer resources than anticipated.
C.
The project is falling behind.
D.
The project is running ahead of schedule.
The Answer Is:
A
This question includes an explanation.
Explanation:
A cost performance index of 1 or greater suggests that project in delivering more with less money; so doing well. Option A is BEST fit for this. CPI = EV/AC (Earned value/ Actual cost)