Given the following estimates: Optimistic 3 days, Pessimistic 9 days, and most likely 6 days,...

Given the following estimates: Optimistic 3 days, Pessimistic 9 days, and most likely 6 days, what is the PERT weighted average?

A.

6

B.

4

C.

6.3

D.

6.1