PMI CA0-001 Question Answer
What are the outputs of Initiation process?
Project charter and PM assigned
Constraints
Assumptions
Al1 of the above
output of Initiation process : Project charter PM assigned Constraints Assumptions
TESTED 22 Feb 2026