Summer Special Limited Time 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 8w52ceb345

An activity that consumes no time or resource and shows only that a dependency exists...

An activity that consumes no time or resource and shows only that a dependency exists between two activities is called:

A.

A milestone

B.

A hammock

C.

A dummy activity

D.

a and c

CA0-001 PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now CA0-001 pdf
Get 60% Discount on All Products, Use Coupon: "8w52ceb345"