Which of the following activities is not part of Plan Risk Management?
A.
Updating risk register
B.
Determining risk roles and responsibilities
C.
Identifying risk categories
D.
Developing a risk management plan
The Answer Is:
A
This question includes an explanation.
Explanation:
Updating the risk register first happens in Identify Risks phase. Determining risk roles and responsibilities, Identifying risk categories and developing a risk management plan are part of Plan Risk Management.