The planner adds stock materials in the maintenance order.

The planner adds stock materials in the maintenance order. Which statements regarding reservations in maintenance orders are correct? Note: There are 2 correct answers to this question.

A.

Open reservations can be cleared when a maintenance order operation is finally confirmed.

B.

For the combination of order type and planner group you can decide when reservations are created.

C.

All open reservations are closed when the maintenance order isset to TECO.

D.

Reservations are created only after a material availability checkhas been performed.