How does a performance-based maintenance plan calculate the interval between start date and planned date?

How does a performance-based maintenance plan calculate the interval between start date and planned date?

A.

Cycle length divided by annual performance

B.

Cycle length divided by monthly performance

C.

Cycle length divided by ((scheduling period) x (cycle modification factor))

D.

Cycle length divided by (annual performance / 365)