Weekend Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: ac4s65

You used reductions to reduce the scheduled duration of all internally-processed activities in your project.

You used reductions to reduce the scheduled duration of all internally-processed activities in your project. However, the duration did not changed after overall network scheduling. What do you check? Note: There are 2 correct answers to this question

A.

If the maximum reduction level is less than 100

B.

If the reduction strategy is set in the network header

C.

If the reduction strategy is set in each activity

D.

If the appropriate reduction type is set in the parameters for network scheduling

C_TS412_2021 PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now C_TS412_2021 pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"