You plan an activity that starts on February 1 and finishes on February 28.

You plan an activity that starts on February 1 and finishes on February 28. For this activity, you want to define a milestone for February 10 which should NOT be changed through scheduling. What do you recommend for milestone definition?

A.

Enter an offset of -18 days to the finish date of the activity

B.

Enter February 10 as fixed date

C.

Enter 10 days as duration

D.

Enter an offset of 10 days to the start date of the activity