In your project.

In your project. You work with a network and external activities. You have created a purchase requisition. The corresponding purchase order is created as well. Now, you increase the quantity of the external activity. How does the system support this scenario?

A.

The purchase order can be updated in Goods Receipt for Purchase Order (MIGO)

B.

The purchase order is updated automatically to match the new quantity while saving the project.

C.

A workflow can be triggered to inform the purchasing group.

D.

The system automatically creates a new purchase requisition with the difference to the original quantity