A user has planned an operation with labor costs and material costs; however, the material...

A user has planned an operation with labor costs and material costs; however, the material cost element is not assigned to a value category.

Where do the material costs appear in the value categories for the order?

A.

In the overhead value category

B.

In a new, automatically created value category

C.

In the unassigned value category

D.

In the internal activity value category