Weekend Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: ac4s65

To link customer inquiry in SD to the project system, you need to assign one...

To link customer inquiry in SD to the project system, you need to assign one or more inquiry items to which of the WBS element?

There are 2 correct answers to this question.

Response:

A.

Billing element

B.

Cost element

C.

Pricing element

D.

Account assignment element