How can the capacity requirements of an activity be reduced?

How can the capacity requirements of an activity be reduced?

There are 3 correct answers to this question.

Response:

A.

With partial confirmations of the activity

B.

By transferring the working times for the activity that was entered in CATS (Cross-Application Time Sheet)

C.

With the period-end closing

D.

By setting the status locked account assignment

E.

With the final confirmation of the activity