You have assigned two resources to the same role resource 1 to calendar week 10...

You have assigned two resources to the same role resource 1 to calendar week 10 and resource 2 to calendar week 11. You want to re-assign resource 2 to calendar week 10 bar the system does not allow you to do so.

What could be a reason for the system behavior?

A.

The role demand for the timeframe is too low

B.

The flexible Assignment indicator is active for the rile type in customizing

C.

The edit in parallel indicator is inactive for the role type in customizing

D.

The assigned effort for either of the resource assigned is to high