Which type of testing should be done after a release upgrade has occurred?
A.
Regression tests
B.
User Acceptance tests
C.
String tests
D.
Integration tests
The Answer Is:
A
This question includes an explanation.
Explanation:
Release upgrades in SAP S/4HANA Cloud Public Edition introduce new features and updates, necessitating testing to ensure system stability.
Option A: Regression testsCorrect. Regression testing is performed after a release upgrade to verify that existing functionalities continue to work as expected. SAP’s official documentation recommends regression testing to validate that new changes do not negatively impact core processes.
Option B: User Acceptance testsIncorrect. User Acceptance Testing (UAT) is typically conducted during the initial implementation or major configuration changes, not specifically after a release upgrade.
Option C: String testsIncorrect. String tests validate specific process flows during implementation, not post-upgrade scenarios.
Option D: Integration testsIncorrect. Integration tests focus on system connectivity during implementation, not post-upgrade validation of existing functionality.
[:, SAP S/4HANA Cloud Testing Guide: Recommends regression testing post-upgrade (https://help.sap.com)., SAP Activate Methodology: Includes regression testing in the Deploy phase for upgrades., SAP S/4HANA Cloud Public Edition Study Guide: Highlights testing strategies for release upgrades., ]
C_S4PM_2504 PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"