You procure some materials exclusively via subcontracting.

You procure some materials exclusively via subcontracting. You want Material Requirements Planning (MRP) to create subcontract purchase requisitions for these materials instead of normal purchase requisitions. What must you do for each of these materials? Note: There are 2 correct answers to this question.

A.

Set a special MRP group for subcontracting in the material master record

B.

Create a bill of material with the components to be provided

C.

Create a routing with an operation to be processed externally

D.

Set a special procurement type for subcontracting in the material master record