When do you specify the data retention period in SAP S/4HANA Migration Cockpit?
A.
When the project status is "Not started"
B.
When the project status is "Finished"
C.
When the project status is "In progress"
D.
When the project status is "Completed"
The Answer Is:
A
This question includes an explanation.
Explanation:
Comprehensive and Detailed in Depth Explanation:
In the SAP S/4HANA Migration Cockpit, the data retention period determines how long migration data (e.g., staging tables or files) is retained before being archived or deleted, aligning with data governance and compliance requirements.
Option A (When the project status is "Not started"): Correct. The retention period is defined during the initial setup of a migration project in the Migration Cockpit, before any data is loaded or processed. This is part of the project configuration in the "Create Project" step, ensuring clarity on data lifecycle management from the outset.
Option B (When the project status is "Finished"): Incorrect. By the "Finished" stage, migration activities are complete, and the retention period is already in effect—changes are no longer allowed.
Option C (When the project status is "In progress"): Incorrect. While adjustments can be made during "In progress," the retention period is a foundational setting established earlier.
Option D (When the project status is "Completed"): Incorrect. "Completed" is not a standard status in the Migration Cockpit; "Finished" is the final status, and retention is predefined.
[References: SAP S/4HANA Cloud Migration Cockpit Guide, "Project Setup and Configuration" (SAP Help Portal)., , , ]
C_S4CFI_2504 PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 60% Discount on All Products,
Use Coupon: "8w52ceb345"