SAP C_C4H510_04 Question Answer
Which of the following options are possible for permissions?
If an activity is contained in multiple views and the access rights are contradictory, the system automatically grants no access.
Unrestricted access rights override any restrictions you have defined.
Restricted access rights override any unrestricted access you have defined.
You can decide, per view, if the access rights should override any restrictions you have defined or not.