You change an active project baseline and save it.

You change an active project baseline and save it. Then, the system creates a new baseline.

What are the statuses of the previous baseline and new baseline?

A.

Previous baseline: "active with pending changes"

New baseline: "in planning"

B.

Previous baseline: "obsolete"

New baseline: "in planning"

C.

Previous baseline: "obsolete"

New baseline: "active"

D.

Previous baseline: "active with pending changes"

New baseline: "in approval"