Which activity helps the project team identify and add user stories to the backlog?
A.
Assessing documentation requirements
B.
Benchmarking current business processes
C.
Planning the release and sprints
D.
Conducting the fit-to-standard workshop
The Answer Is:
D
This question includes an explanation.
Explanation:
The fit-to-standard workshop is a key activity in SAP Activate that involves aligning SAP standard processes with business requirements. During this workshop, the team identifies gaps and additional requirements, which are then translated into user stories and added to the backlog for implementation.References:SAP Activate Methodology, Fit-to-Standard Workshops, Backlog Management