A federated model has been created for a multidisciplinary project, but clashes are being reported...

A federated model has been created for a multidisciplinary project, but clashes are being reported in areas where coordination should already be resolved. Upon investigation, the BIM manager finds that some models were exported with outdated links and local coordinates.

What is the most appropriate next step before proceeding with coordination analysis?

A.

Instruct teams to verify model references and coordinate systems before reassembly.

B.

Freeze the current model state and ask trades to work around the identified issues.

C.

Notify the client and exclude the faulty models from further coordination.

D.

Run an additional clash-detection pass with adjusted tolerance thresholds to reduce clash totals.

BIM_MGT_101 PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now BIM_MGT_101 pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"