Which action should be completed by the Pittville Project Board?

Which action should be completed by the Pittville Project Board?

A.

Approve the continuation of the project at the end of each delivery stage.

B.

Plan, in detail, the construction of the new learning campus.

C.

Produce regular progress reports for the Senior Responsible Owner of the project.

D.

Document the project risks in the risk log.