Refer to the exhibit.

Refer to the exhibit.

Xpert Ltd uses a standard costing system and therefore values all inventory at standard cost. During period 7, the price paid for material 'Z' was £2 per kg more than the standard price.

The following information for material 'Z' relates to period 7:

What was the material price variance for 'Z' in period 7?

A.

£2 adverse

B.

£40 adverse

C.

£400 adverse

D.

£500 adverse