You tend to be conservative in your project estimations because you know how many things...

You tend to be conservative in your project estimations because you know how many things can go wrong and extend the schedule. You manager is not happy with your estimates and thinks you are being too negative with your numbers and not trying hard enough Which estimation method should you use to provide your manager with a positive' number while still also providing the number you think is more realistic?

A.

Wideband defphi

B.

Planning poker

C.

Three-point estimation

D.

Extrapolation