Which type of testing would BEST demonstrate to clients that a completed security system ' s physical and functional requirements comply with the contract requirements?

A.

Site acceptance testing

B.

Post implementation testing

C.

Reliability or availability testing

D.

Pre-delivery or factory acceptance testing